Hubby digging out to pour a spread footing for the front stone steps up to the covered front porch.
Plumbing fixtures going in... nice guest bath room tub.
Framing in for the Master Bath jacuzzi tub!
Plumbing on one side of the Master Bath walk-in shower.
Can lights and overhead rain shower head piping in Master Bath walk-in shower.
Plumbing on the other side of Master Bath walk-in shower with other shower head.
Mason working on chimney stone.
Hubby is constructing his formwork to pour his concrete footings for the front steps and the stone foundation walls under the perimeter of the covered porch.
Chimney stone is complete!
The ceiling wood is going in under the "Porte Cochere"/carport and porches!!!
Looks so good!
Mason is starting the outside fireplace stone at the same time as the ceiling wood installation!
Porte Cochere ceilings are done!
The high-up dormer windows are in!
The Master tub is set!
Fireplace is done.
Doggie paw prints in the footing!
Foundation wall footings are poured.
Foundation block installed.
Rear view with high windows and porch wood ceilings.